Ruling removes a legal obstacle to Resilient Technology Park as STACK Infrastructure advances its $18 billion regional development
SHREVEPORT, La. — A Louisiana appeals court has upheld the City of Shreveport’s approval of a major Amazon Web Services data center in west Shreveport, rejecting a legal challenge to the project at Resilient Technology Park.
The Second Circuit Court of Appeal ruled Wednesday, Nov. 18, in favor of the city, affirming a lower court decision that upheld the Shreveport City Council’s approval of a special-use permit for the development near Greenwood Road.
The ruling removes a significant legal obstacle for one of three data center campuses being developed by STACK Infrastructure in Northwest Louisiana.
The dispute began in December 2025, when the Shreveport-Caddo Metropolitan Planning Commission denied the permit application following concerns from nearby residents about utilities, traffic, noise and neighborhood impacts.
The Shreveport City Council subsequently overturned that decision, prompting a lawsuit from three plaintiffs who challenged the city’s approval process.
In its ruling, the appellate court found that the City Council had acted within its authority and adequately considered the applicable development standards. The judges also rejected arguments that nondisclosure agreements involving city officials justified overturning the approval.
The decision leaves the special-use permit in place, although further judicial review may still be sought.
Construction moving forward
The ruling comes as STACK Infrastructure advances construction across three Northwest Louisiana sites: Resilient Technology Park in west Shreveport, Stateline Road near Blanchard and Louisiana Highway 3 near Benton.
Together, the developments represent approximately $18 billion in planned investment.
At the Bossier Chamber of Commerce’s State of the Community event earlier this month, STACK representative Josh Fenn said construction was underway at all three locations, including initial mobilization at Resilient Technology Park.
The company is targeting its first operational buildings in mid-to-late 2027, with full campus completion anticipated around 2029.
E.E. REED East Coast has been selected as general contractor for the west Shreveport project.
While the court’s decision resolves the appeal before the Second Circuit, the development remains subject to applicable construction and permitting requirements.
The ruling marks another step forward for a regional investment expected to generate substantial construction activity, permanent employment and increased demand for infrastructure and utilities.