Saturday, April 20, 2024

I-20 overlay project to go to bid May 10

by BIZ Magazine

By Stacey Tinsley, Bossier Press-Tribune

A much smoother ride is on the horizon for drivers along I-20 in Bossier City.

The future I-20 overlay project is scheduled to go to bid on May 10, 2023. Due to rising costs and inflation, the estimated cost of the project is now $93 million. It was previously $55 million when it went to bid in November 2021.

“That’s when the bids came in extremely high, were reviewed, and ultimately rejected. Also, the cost is because it’s not simply an overlay project,” said Erin Buchanan, spokesperson for the Louisiana Department of Transportation and Development. “All of the roadway down to the base is being completely removed and rebuilt, from just west of Benton Road to Industrial Drive, including the on and off-ramps at each interchange. Additionally, concrete repairs are included along the I-20 corridor in Shreveport as far west as Pines Road, and in Bossier as far east as I-220 (outside of the major rehabilitation section).”

Once the project goes to bid, an apparent low bidder will be identified. Depending on the amount, the bid may have through the review process before the contract can be executed and awarded. Following that, DOTD will have a pre-construction conference with the contractor to identify a start date for construction.

“The project has an estimated construction time of approximately two to two-and-a-half years. However, the prospective contractors will bid the number of days they determine to be reasonable in order to complete the work,” said Buchanan.

Additional information on this project will be released once the project is bid and a contract is awarded to a contractor.

You may also like

-
00:00
00:00
Update Required Flash plugin
-
00:00
00:00